This is a message to keep everyone up to date on developments to get Rink 1 available for play.
Representatives of Cavendish Surveyors and Maclen Property Services visited early on Friday 11/10/24 to look at temporary repairs to the wall and see us through safely to the main repairs in May 2025.
They came up with a plan to fit a temporary plywood stud wall anchored to the steels either side of and along the bottom of the damaged area. This should be a quick and inexpensive procedure. We were happy with this plan and are awaiting a quote from Maclen. We stressed it was important that this went ahead asap and a maximum time of 23/10/24 was not dismissed by the builders. We are awaiting the quote.
Thank you. Alasdair.